FC Commissioners information
Earlier this week I wrote an article concerning the amount of storm damage done to Franklin County infrastructure during the several major storms in June. In the article, it was discussed by the county’s Emergency Management Agency Director Amy Lindsey at the most recent FC commissioners’ meeting, the state and federal governments would probably be unable to assist the county in any meaningful way.
FC Commissioners produced this information concerning the damage.
This list does not include any damage done during the severe flooding in Franklin County’s southern area on Wednesday, June 30.
Bath Rd – Culvert and asphalt repair $75,000
H Meyer Rd – Culvert and asphalt repair $65,000
Glockners Creek – Repair wash out and asphalt $55,000
Barber Rd – Repair Road encroachment and asphalt $175,000
Hetrick Rd – Pipe repair and armament of bank $58,000
Possum Hollow – Pipe repair and armament of bank $165,000
Wewe Hill – drainage and dirt work and asphalt $45,000
Graf – drainage and dirt work and asphalt $55,000
Goblets Knob – drainage and dirt work and asphalt $50,000
Whitcomb Rd – headwall repair and pipe replacement $100,000
St Peters Rd – headwall repair (two locations) and asphalt $125,000
County Line – Culvert repair and asphalt $55,000
Five point Rd – asphalt $40,000
Loop Rd – pipe and asphalt $12,000
Bull Fork slab – repair damage eroded slab and add armament $100,000
North Hamburg Rd – slide repair $1,200,000
Whistle Creek – armament of bank and asphalt $75,000
Whistle Creek Rd – armament of bank and asphalt $60,000
Frazier Rd – armament of bank and asphalt $85,000
Pine Rd – Pipe repair, bank encroachment, armament and install concrete wall $950,000
Pipe Creek – asphalt, repair encroachment, armament $900,000
Pipe Creek Rd – Slide – $250,000
Blue Creek – slide and encroachment repair, armament $1,100,000
Levee Rd – replace plugged structure, slide and encroachment repair, armament $300,000
Russell Rd – structure damage $50,000
Silver Creek Bridge been closed for five to six years, needs demolition to remove old bridge causing private property to flood $100,000
Silver Creek Bridge – replaced $1,500,000
North Hamburg Bridge $520,000 (our portion) needs to be budgeted for storm damage to Snail Creek Bridge and other structures on Snail Creek $400,000
Sanes Creek Bridge – March 2020 storm damage $800,000 – needs on list to replace ASAP
Numerous locations not mentioned, causing $1-2,000 damage per location. Estimating $100,000 in damages