Resurfacing to begin on Ind. 129 south of Batesville

INDOT press release

RIPLEY COUNTY— Indiana Department of Transportation contractor Dave O’Mara Contractor Inc. plans to begin asphalt resurface work on Indiana 129 next week south of Batesville in Ripley County. On or after Monday, June 28, crews are scheduled to start patching between Ind. 48 and Ind. 46.

Starting around mid-July, crews are expected to begin milling and paving. Traffic will be maintained under lane closures with flagging. The $2.4 million contract was awarded in October 2020 and should be complete by the end of August.

Motorists are reminded to slow down, use extra caution, and drive distraction-free in and near construction zones. All work is weather-dependent and schedules are subject to change.

S.R. 129 - Ripley County

Stay Informed
Motorists in Southeast Indiana can monitor road closures, road conditions, and traffic alerts any time via: