By John Estridge
U.S. 27’s paving project between Liberty and Richmond should be completed by mid-November.
Indiana Department of Transportation released that information Monday morning, Aug. 3.
According to Greenfield District Communication Director Mallory Duncan, the paving project is on schedule. It is estimated to cost around $5.8 million. The contractor is finishing up the patching portion and will move to milling and paving the end of August/early September. The project is scheduled to be completed by mid-November, she said.